Day 6


After a week all the ground floor windows were in. The hole was knocked though into the side of the house where, and two large lintels were put in place. It's amazing how large a hole you can cut in brickwork, without it falling down!

Day 7


The scaffolding arrived Wednesday morning. The floor joists were cut to length ready for building into the blockwork.

Day 9


There where a lot of wooden brackets made to tilt the hanging tiles out from the wall at the bottom. The lintels above all the windows are in place.



Day 10


The bricklayers are now now getting through blocks at an alarming rate, we've had more than 500 delivered in the space of two days.


At the end of the second week, we're up to the level of the bedroom window cills. The ground floor rooms are starting to look really cavernous, what was a plan outline for so long has suddenly been transformed into a three dimensional object.

After twelve days things are slowing up a bit, the bricklayers only turned up two days in the last week. The wall plates are in and we're waiting for the carpenter to start the roof.